Dungeness

There are two adjacent nuclear power station sites at Dungeness:

  • Dungeness A;
  • Dungeness B.

Dungeness A

Dungeness A comprises of two Magnox reactors that generated electricity from 1965 till 2006. Defuelling of the twin reactors was scheduled to commence in 2007 and to be completed in 2009.

Location

Kent

Nuclear operation period

Operated from 1965 to 2006

Status

Defuelling/Decommissioning

Site licensee

Magnox Electric Ltd

Responsible organisation

Nuclear Decommissioning Authority

Dungeness A

Dungeness A Magnox power station

Dungeness B

Dungeness B AGR power station


Dungeness B

Dungeness B comprises of two operating Advanced Gas-Cooled Reactors (AGR) that became operational in 1983. It is expected that the station will continue generating electricity up to 2018.

Location

Kent                                                                     

Nuclear operation period

Operating since 1983

Status

Operational

Site licensee

British Energy

Responsible organisation

British Energy


Inventory Documents

Find documents specific to the radioactive wastes managed on Dungeness in Inventory Documents.

site location map

See also...

British Energy website
Magnox North Ltd Website
Nuclear Decommissioning Authority (NDA) website