Search for Articles
Insight Newsletter

Insight Newsletter - Edition 3
(1Mb)
If you have any comments on Insight, please contact the editor:
01925 802343
Latest Articles
02 September 2010
Shared learning on new waste storage guidelines
01 September 2010
Welsh Secretary of State visits Wylfa site
31 August 2010
Research reactor ZEBRA returns to grass
27 August 2010
Fuel removal milestone at Chapelcross
26 August 2010
Commercial strategy update
18 August 2010
Insight into civil nuclear supply chain
09 August 2010
Research provides design options
30 July 2010
Site representatives visit Dounreay
30 July 2010
Forthcoming publications
15 July 2010
Shared lessons on safety
Major hazard eliminated
25 January 2010

Dounreay achieved yet another major milestone in January – with the completion of a seven-year project to clean up the dirtiest area of Dounreay's uranium conversion plant.
When the plant was operating (1957-1998) the 'amber' area was a high-activity, high-contamination area. It housed equipment to dissolve uranium in acid so that reusable material could be recovered and waste products removed.
The nature of this work caused high levels of contamination and workers tasked with cleaning up the area were forced to wear cumbersome air-fed suits before they could enter.
The NDA was very keen to see the clean-up of this area, which was also classed as a high priority by the Nuclear Installations Inspectorate, completed on time – which it was.
Before any clean-up work could start, the ventilation system had to be modernised to ensure that it was adequate for the work and to ensure worker safety. Redundant glove boxes and solvent extraction plant were then stripped out, cleaned up and cut up before being packaged as waste.
The four-inch thick slab tanks that once held radioactive liquid were removed, and the team employed a Brokk remotely operated demolition robot to help them demolish the 32 reinforced concrete plinths that separated the tanks.
Approximately 130 tonnes of concrete rubble was sentenced as low level waste.

Randall Bargelt, the NDA's Dounreay Site Director, said:
"We are very pleased to see yet another major hazard at Dounreay eliminated.
"This was a big job, and the team made steady progress by tackling it bit by bit – proving that they can take on large decommissioning jobs and get them done.
"The current competition for Dounreay will help to drive these sorts of results even further, and we are looking forward to seeing what potential bidders have to offer".
- More information via Dounreay Site Restoration Ltd website
