Future Plans

This section provides a brief description of the Windscale site as outlined in the NDA's strategy.

The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.


Site End States

Brown field under institutional control.

Current Key Milestones

 Year

 Milestones

 2013 Pile 2 care and maintenance - removal of isotopes and replacement of building with low containment structure
 2015 Removal of WAGR and associated buildings - dismantling and demolition of B50 and B52
 2015 Demolition of redundant buildings - buildings demolished to ground level with foundations remaining
 2015 Pile 1 care and maintenance - removal of fuel and isotopes and replacement of building with low containment structure
 2020 Completion of tenant operations in B13 - Nexia's current lease expires (may be extended)
 2025 Demolition of B13
 2040 Transfer of ILW to final storage, removal of waste from B64 ILW store, commence dismantling of the piles safe store
 2065 Final site clearance and closure