Performance Updates
Find out more about Trawsfynydd's Performance, visit our Programme Performance Updates section.
See also
NDA Strategy Document

We are in the process of revising
the Strategy that was approved by
Government in 2006:
Strategy (approved by Government 2006) (3Mb)
We are consulting on our Draft Strategy until 24 November 2010:

More information on Draft Strategy
Find more documents in our comprehensive Document Library.
Future Plans
This section provides a brief description of the Trawsfynydd site as outlined in the NDA's strategy.
The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.
Site End States
| Current plans are to delicense the site for reuse in future recreational purposes to reflect its location within the Snowdonia National Park. |
Current Key Issues
| Year | Milestones |
|---|---|
| 2007 | Completion of ILW store for storage of processed operational waste |
| 2011 | Demolition of ponds complex |
| 2012 | Enter care and maintenance |
| 2040 | Packaged ILW transported to repository |
| 2046 | Demolition of waste store in line with local planning permissions and public enquiry findings |
| 2088 | Start of final site clearance |
| 2096 | Final site clearance and closure |