Location

Sellafield Location

Web Updates

Keep informed with the latest news and developments from the NDA

Performance Updates

Find out more about Sellafield (including Calder Hall and Windscale)'s Performance, visit our Programme Performance Updates section.

See also

Site Progress Key

On target
On target
Behind target with possibility of recovery
Behind target with possibility of recovery
Behind target
Behind target

Safety and Environmental Performance Key

Nuclear Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more INES Level 1 or above in the month
Industrial Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more RIDDOR reportable events in the month
Environmental Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more environmental non compliances in the month
.
Home > Our Sites > Sellafield (including Calder Hall and Windscale)  

Sellafield (including Calder Hall and Windscale)

Sellafield site 

Sellafield
Seascale 
Cumbria
CA20 1PG

Tel. 019467 28333

Sellafield is a large and complex nuclear chemical facility located in West Cumbria. The site has played a pivotal role within the nuclear industry since the 1940s. Site operations include fuel reprocessing, fuel fabrication and storage of nuclear materials and radioactive wastes.

Calder Hall, located on the site, was the world's first commercial nuclear power station. Generation started in 1956 and ceased in 2003.

Windscale, also located on the site, comprises three reactors. Two of the reactors were shut down in 1957 and the third one was closed in 1981. Substantial damage by fire to one of the reactors in 1957 has created significant additional decommissioning challenges.

Overview

Age Operated since 1947
Site Stakeholder Group West Cumbria Site Stakeholder Group (WCSSG)
Site Licensee Sellafield Limited
Parent Body Organisation Nuclear Management Partners (NMP) Ltd
Status Defuelling and Partial Decommissioning
Cost - Lifetime
(total discounted nuclear liability)
£32,066m

 * The costs of discharging the nuclear liability will be incurred over a significant period of time. To take account of the time value of money, the costs are "discounted" back to a present value. Effectively this is the amount that would need to be invested today, at a set rate of interest (the discount rate) in order to pay for the liability in the future as it falls due.

Year Key Activities

2120

Final site clearance

2105 -
2115

Calder Hall final site clearance

2075

Transfer of stored HLW to HLW repository

2046

All ILW from the Legacy Ponds and Silos retrieved, conditioned and stored

2040

Transfer of stored ILW to Geological Disposal Facility (GDF)

2030

Windscale Pile 1 and 2 in Care and Maintenance with fuel and isotopes removed

2026

Vitrification of liquid HLW complete

First Generation Magnox Storage Pond - start of residual retrievals

2024

Calder Hall site enters Care and Maintenance phase
During this stage the reactor is left to cool. Most of the structures are removed, and the reactor building is left in a safe state which requires minimum supervision, until final site clearance.

2021

Vitrification of liquid HLW complete

2019

Complete return of overseas customers HLW

2018

Pile Fuel Cladding Silo - start of waste retrievals

Magnox Swarf Storage Silos - start of bulk retrievals

THORP reprocessing complete

2017

Pile Fuel Storage Pond - start of residual retrieval

2016

Magnox reprocessing completed

2015

Highly Active Liquor (HAL) stocks reduced to "steady state" volume

First Generation Magnox Storage Pond - start of bulk retrievals

2014

Completion of defuelling at Calder Hall

2013

Complete Active commissioning of Sellafield Product and Residue Store (SPRS)


Progress against this year's targets

Status as at end Quarter 3 (end December 2011) - next update due April 2012


Site Restoration

Target Status Commentary

Continue programme of asset improvements to manage ageing infrastructure of plant and buildings

On target

On track

Ongoing decommissioning and demolition of redundant facilities, specifically:

Progress critical path activities to deliver the replacement Separation Area Ventilation stack, which will enable the demolition of the First Generation Reprocessing plant venticlation stack

On target

On track

Progress critical path activities to the start of retrievals for legacy wastes, specifically:

First Generation Magnox Storage Pond - completion of new skip handler tooling and completion of integration works testing

Behind target

NDA set a stretch target for 2011/12, completion to this date will not be met but completion is still in line with base date in 2012/13.

Progress critical path activities to the start of retrievals for legacy wastes, specifically:

Magnox Swarf Storage Silos - complete the construction of Retrievals Machine 2 and start factory acceptance testing

Behind target

Will be delivered within the year but this will be later than the date originally expected by the NDA.

 

Progress critical path activities to the start of retrievals for legacy wastes, specifically:

* Magnox Swarf Storage Silos - progress the design for the waste encapsulation and waste product transfer capability

On target

On track

Progress critical path activities to the start of retrievals for legacy wastes, specifically:

Pile Fuel Cladding Silo - commence stage 2 construction of the 'Superstructure' and control room

Behind target

NDA set a stretch target for 2011/12, completion to this date will not be met but completion is still in line with base date in 2012/13.

 

Progress critical path activities to the start of retrievals for legacy wastes, specifically:

Pile Fuel Storage Pond - progress active commissioning of the local sludge treatment plant storage tanks

 

The project has completed Inactive commissioning  and is on programme to demobilise by the end of the FY. However reduced sludge arisings from retrievals to date mean that an early commitment of the facility to active operations is not required.  Alternative strategies are being considered.

 

Continue to process legacy uranium hexafluoride bottles

On target

On track

Nuclear Materials

Target Status Commentary

 Continue the safe storage of uranium

On target

Uranium continues to be stored safely. Cans forecast to be transferred to SPRS this year is lower than planned due to equipment calibration issues.

 

 Work on solutions to reduce the hazard associated with the uranium hexafluoride tails

On target

On track

Continue active commissioning of Sellafield Product and Residue Store (SPRS)

On target

On track

Spent Fuels

Target Status Commentary

Continue to reprocess fuel through THORP; this includes fuel from EDF Energy as well as overseas oxide fuel

On target

On track

Continue to reprocess Magnox Fuel

Behind target

Target set for this financial year will not be met.

 

Progress the capability to receive and reprocess Dounraey Fast Reactor (DFR) breeder fuel at Sellafield

On target

On track

Integrated Waste Management

Target Status Commentary

Continue the construction of Evaporator D to provide additional evaporative capacity - complete critical path activities, specifically:

Complete sea delivery module for Evaporator D and commence installation

On target

1st module delivered at the beginning of June (complete)

Continue to process uranic residues

On target

On track

Continue to retrieve and treat, for long-term storage, legacy flocculent from the flocculent storage tanks

On target

NDA target for this year completed in Sept 2011.

Continue to transfer legacy Plutonium Contaminated Material (PCM) to modern engineered stores

On target

On track

Continue to export vitrified Highly Active Liquor (HAL) to overseas customers

On target

Targets set for this year have been met.

Ongoing waste treatment activities to support both commercial operations and decommissioning, such as:

Plutonium Contaminated Materials (PCM) processed through the Waste Treatment Complex (WTC)

 

On target

Target exceeded

Continue to process Highly Active Liquor (HAL) through the vitrification plant

Behind target with possibility of recovery

Target set for this financial year is in jeopardy

 

Business Optimisation

Target Status Commentary

Sellafield MOX plant - progress critical path activities to deliver the new rod line

 

At the end of Quarter 1 2011/12 target was on track. Subsequently, on 3 August 2011, NDA announced the closure of the Sellafield MOX plant.

Critical Enablers

Target Status Commentary

Sellafield Integrated Change Programme (ICP) - continued delivery of the ICP improvement programme driving performance specifically:

Flexible permissioning of work activities

On target

On track

Sellafield Integrated Change Programme (ICP) - continued delivery of the ICP improvement programme driving performance specifically:

Increased mobility and flexibility of workforce

On target

On track

Sellafield Integrated Change Programme (ICP) - continued delivery of the ICP improvement programme driving performance specifically:

New arrangements for the production of safety cases at Sellafield - pilot projects to be completed and new arrangements embedded

On target

On track


Safety and Environmental Performance

Status as at end Quarter 3 (end December 2011) - next update due April 2012

Nuclear Safety
Industrial Safety
Environmental Safety