Performance Updates
Find out more about Sellafield (including Calder Hall and Windscale)'s Performance, visit our Programme Performance Updates section.
See also
Site Progress Key
On target |
On target |
Behind target with possibility of recovery |
Behind target with possibility of recovery |
Behind target |
Behind target |
Safety and Environmental Performance Key
| Nuclear Safety | |
|---|---|
|
|
No incidents in the month |
|
|
One or more INES Level 1 or above in the month |
| Industrial Safety | |
|
|
No incidents in the month |
|
|
One or more RIDDOR reportable events in the month |
| Environmental Safety |
|
|
|
No incidents in the month |
|
|
One or more environmental non compliances in the month |
Sellafield (including Calder Hall and Windscale)
Sellafield
Seascale
Cumbria
CA20 1PG
Tel. 019467 28333
Sellafield is a large and complex nuclear chemical facility located in West Cumbria. The site has played a pivotal role within the nuclear industry since the 1940s. Site operations include fuel reprocessing, fuel fabrication and storage of nuclear materials and radioactive wastes.
Calder Hall, located on the site, was the world's first commercial nuclear power station. Generation started in 1956 and ceased in 2003.
Windscale, also located on the site, comprises three reactors. Two of the reactors were shut down in 1957 and the third one was closed in 1981. Substantial damage by fire to one of the reactors in 1957 has created significant additional decommissioning challenges.
Overview
| Age | Operated since 1947 |
|---|---|
| Site Stakeholder Group | West Cumbria Site Stakeholder Group (WCSSG) |
| Site Licensee | Sellafield Limited |
| Parent Body Organisation | Nuclear Management Partners (NMP) Ltd |
| Status | Defuelling and Partial Decommissioning |
| Cost - Lifetime (total discounted nuclear liability) |
£32,066m |
* The costs of discharging the nuclear liability will be incurred over a significant period of time. To take account of the time value of money, the costs are "discounted" back to a present value. Effectively this is the amount that would need to be invested today, at a set rate of interest (the discount rate) in order to pay for the liability in the future as it falls due.
| Year | Key Activities |
|---|---|
|
2120 |
Final site clearance |
|
2105 - |
Calder Hall final site clearance |
|
2075 |
Transfer of stored HLW to HLW repository |
|
2046 |
All ILW from the Legacy Ponds and Silos retrieved, conditioned and stored |
|
2040 |
Transfer of stored ILW to Geological Disposal Facility (GDF) |
|
2030 |
Windscale Pile 1 and 2 in Care and Maintenance with fuel and isotopes removed |
|
2026 |
Vitrification of liquid HLW complete First Generation Magnox Storage Pond - start of residual retrievals |
|
2024 |
Calder Hall site enters Care and Maintenance phase |
|
2021 |
Vitrification of liquid HLW complete |
|
2019 |
Complete return of overseas customers HLW |
|
2018 |
Pile Fuel Cladding Silo - start of waste retrievals Magnox Swarf Storage Silos - start of bulk retrievals THORP reprocessing complete |
|
2017 |
Pile Fuel Storage Pond - start of residual retrieval |
|
2016 |
Magnox reprocessing completed |
|
2015 |
Highly Active Liquor (HAL) stocks reduced to "steady state" volume First Generation Magnox Storage Pond - start of bulk retrievals |
|
2014 |
Completion of defuelling at Calder Hall |
|
2013 |
Complete Active commissioning of Sellafield Product and Residue Store (SPRS) |
Progress against this year's targets
Status as at end Quarter 3 (end December 2011) - next update due April 2012
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Continue programme of asset improvements to manage ageing infrastructure of plant and buildings |
On target |
On track |
Ongoing decommissioning and demolition of redundant facilities, specifically: Progress critical path activities to deliver the replacement Separation Area Ventilation stack, which will enable the demolition of the First Generation Reprocessing plant venticlation stack |
On target |
On track |
Progress critical path activities to the start of retrievals for legacy wastes, specifically: First Generation Magnox Storage Pond - completion of new skip handler tooling and completion of integration works testing |
Behind target |
NDA set a stretch target for 2011/12, completion to this date will not be met but completion is still in line with base date in 2012/13. |
Progress critical path activities to the start of retrievals for legacy wastes, specifically: Magnox Swarf Storage Silos - complete the construction of Retrievals Machine 2 and start factory acceptance testing |
Behind target |
Will be delivered within the year but this will be later than the date originally expected by the NDA.
|
Progress critical path activities to the start of retrievals for legacy wastes, specifically: * Magnox Swarf Storage Silos - progress the design for the waste encapsulation and waste product transfer capability |
On target |
On track |
Progress critical path activities to the start of retrievals for legacy wastes, specifically: Pile Fuel Cladding Silo - commence stage 2 construction of the 'Superstructure' and control room |
Behind target |
NDA set a stretch target for 2011/12, completion to this date will not be met but completion is still in line with base date in 2012/13.
|
Progress critical path activities to the start of retrievals for legacy wastes, specifically: Pile Fuel Storage Pond - progress active commissioning of the local sludge treatment plant storage tanks |
The project has completed Inactive commissioning and is on programme to demobilise by the end of the FY. However reduced sludge arisings from retrievals to date mean that an early commitment of the facility to active operations is not required. Alternative strategies are being considered.
|
|
Continue to process legacy uranium hexafluoride bottles |
On target |
On track |
Nuclear Materials
| Target | Status | Commentary |
|---|---|---|
Continue the safe storage of uranium |
On target |
Uranium continues to be stored safely. Cans forecast to be transferred to SPRS this year is lower than planned due to equipment calibration issues.
|
Work on solutions to reduce the hazard associated with the uranium hexafluoride tails |
On target |
On track |
Continue active commissioning of Sellafield Product and Residue Store (SPRS) |
On target |
On track |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Continue to reprocess fuel through THORP; this includes fuel from EDF Energy as well as overseas oxide fuel |
On target |
On track |
Continue to reprocess Magnox Fuel |
Behind target |
Target set for this financial year will not be met.
|
Progress the capability to receive and reprocess Dounraey Fast Reactor (DFR) breeder fuel at Sellafield |
On target |
On track |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Continue the construction of Evaporator D to provide additional evaporative capacity - complete critical path activities, specifically: Complete sea delivery module for Evaporator D and commence installation |
On target |
1st module delivered at the beginning of June (complete) |
Continue to process uranic residues |
On target |
On track |
Continue to retrieve and treat, for long-term storage, legacy flocculent from the flocculent storage tanks |
On target |
NDA target for this year completed in Sept 2011. |
Continue to transfer legacy Plutonium Contaminated Material (PCM) to modern engineered stores |
On target |
On track |
Continue to export vitrified Highly Active Liquor (HAL) to overseas customers |
On target |
Targets set for this year have been met. |
Ongoing waste treatment activities to support both commercial operations and decommissioning, such as: Plutonium Contaminated Materials (PCM) processed through the Waste Treatment Complex (WTC)
|
On target |
Target exceeded |
Continue to process Highly Active Liquor (HAL) through the vitrification plant |
Behind target with possibility of recovery |
Target set for this financial year is in jeopardy
|
Business Optimisation
| Target | Status | Commentary |
|---|---|---|
Sellafield MOX plant - progress critical path activities to deliver the new rod line |
At the end of Quarter 1 2011/12 target was on track. Subsequently, on 3 August 2011, NDA announced the closure of the Sellafield MOX plant. |
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Sellafield Integrated Change Programme (ICP) - continued delivery of the ICP improvement programme driving performance specifically: Flexible permissioning of work activities |
On target |
On track |
Sellafield Integrated Change Programme (ICP) - continued delivery of the ICP improvement programme driving performance specifically: Increased mobility and flexibility of workforce |
On target |
On track |
Sellafield Integrated Change Programme (ICP) - continued delivery of the ICP improvement programme driving performance specifically: New arrangements for the production of safety cases at Sellafield - pilot projects to be completed and new arrangements embedded |
On target |
On track |