Future Plans
This section provides a brief description of the Oldbury site as outlined in the NDA's strategy.
The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.
Site End States
| The current assumption is that the site will be delicensed and returned to its former use as agricultural land. |
Current Key Milestones
| Year | Milestones |
|---|---|
| 2008 | Cease generation |
| 2009 | Commence defuelling |
| 2010 | Complete defuelling |
| 2010 | Care and maintenance preparations begin |
| 2023 | Care and maintenance commences |
| 2109 | Final site clearance begins |
| 2118 | Final site clearance and closure |