Location

Oldbury Location

Web Updates

Keep informed with the latest news and developments from the NDA

Performance Updates

Find out more about Oldbury's Performance, visit our Programme Performance Updates section.

See also

Related Documents

Site Progress Key

On target
On target
Behind target with possibility of recovery
Behind target with possibility of recovery
Behind target
Behind target

Safety and Environmental Performance Key

Nuclear Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more INES Level 1 or above in the month
Industrial Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more RIDDOR reportable events in the month
Environmental Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more environmental non compliances in the month
.
Home > Our Sites > Oldbury  

Oldbury

Oldbury Site 

Oldbury Power Station
Oldbury Naite
Thornbury
South Gloucestershire
BS35 1RQ
01454 893500

Oldbury power station is located in South Gloucestershire and has an area of 51 hectares covered by the nuclear site licence. It started electricity generation in 1967. The area around the site is environmentally sensitive and has been designated as a Special Protection Area (SPA) and a Site of Special Scientific Interest (SSSI).

Overview

Age Operated from 1967
Site Stakeholder Group Oldbury Site Stakeholder Group
Site Licensee Magnox Limited
Parent Body Organisation Energy Solutions Inc
Status Operational
Cost - Lifetime
(total discounted nuclear liability)
£939m

 * The costs of discharging the nuclear liability will be incurred over a significant period of time. To take account of the time value of money, the costs are "discounted" back to a present value. Effectively this is the amount that would need to be invested today, at a set rate of interest (the discount rate) in order to pay for the liability in the future as it falls due.

Year Key Activities

2092 -
2101

Final site clearance

2027

Site enters Care and Maintenance phase
During this stage the reactor is left to cool. Most of the structures are removed, and the reactor building is left ina safe state which requires minimum supervision, until final site clearance.

2014

Completion of defuelling
Once a site has finished operating and the fuel has cooled down it can beremoved and taken to Sellafield for reprocessing.

2012 Cease generation

Progress against this year's targets

Status as at end Quarter 3 (end December 2011) - next update due April 2012


Site Restoration

Target Status Commentary

Preparations for decommissioning and hazard reduction

On target

On track

Spent Fuels

Target Status Commentary

Commencement of reactor bulk defuelling in line with MOP requirements (following cessation of generation)

On target

On track

Business Optimisation

Target Status Commentary

Continued electricity generation

On target

On track

Critical Enablers

Target Status Commentary

Commencement of the organisational change programme for decommissioning

On target

On track


Safety and Environmental Performance

Status as at end Quarter 3 (end December 2011) - next update due April 2012

Nuclear Safety
Industrial Safety
Environmental Safety