No pages meet the criteria

Location

Sellafield Location

Web Updates

Keep informed with the latest news and developments from the NDA

Performance Updates

Find out more about LLWR's Performance, visit our Programme Performance Updates section.

See also

Related Documents

Site Progress Key

On target
On target
Behind target with possibility of recovery
Behind target with possibility of recovery
Behind target
Behind target

Safety and Environmental Performance Key

Nuclear Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more INES Level 1 or above in the month
Industrial Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more RIDDOR reportable events in the month
Environmental Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more environmental non compliances in the month
.
Home > Our Sites > Low Level Waste Repository  

Low Level Waste Repository

Low Level Waste Repository - A forklift moving containers in the Vault 

LLW Repository near Drigg
Holmrook
Cumbria
CA19 1XH

Tel. 01946 724800

This Low Level Waste (LLW) Repository has operated as a national LLW disposal facility since 1959. Wastes are compacted and placed in containers before being transferred to the facility. Following a major upgrade of disposal operations in 1995, all LLW is now disposed of in engineered concrete vaults.

Plutonium Contaminated Materials are being removed from the site for long-term storage at nearby Sellafield.

Overview

Age Operated from 1959
Site Stakeholder Group West Cumbria Sites Stakeholder Group
Site Licensee LLW Repository Ltd
Parent Body Organisation UK Nuclear Waste Management Limited
Status Operational
Cost - Lifetime
(total discounted nuclear liability)
£252m

 * The costs of discharging the nuclear liability will be incurred over a significant period of time. To take account of the time value of money, the costs are "discounted" back to a present value. Effectively this is the amount that would need to be invested today, at a set rate of interest (the discount rate) in order to pay for the liability in the future as it falls due.

Year Key Activities

2080

Final site clearance achieved

2018

PCM facilities removal complete

2007 -
2055

Engineered vaults construction


Progress against this year's targets

Status as at end of financial year 2012/13 (Progress against Quarter 1 of 2012/13 will be reported in July 2013)


Site Restoration

Target Status Commentary

Commence site preparation for phased construction of final cap

On target

12/13 Target Complete

Ongoing decommissioning of PCM facilities

Behind target

Milestones have been completed but late to schedule due to a change to the delivery strategy during the year

Ongoing implementation of the Environmental Safety Case

On target

12/13 Target Complete


Safety and Environmental Performance

Status as at end of financial year 2012/13 (Progress against Quarter 1 of 2012/13 will be reported in July 2013)

Nuclear Safety
Industrial Safety
Environmental Safety