Future Plans

Location

Hunterston Location

Performance Updates

Find out more about Hunterston A's Performance, visit our Programme Performance Updates section.

See also

NDA Strategy Document

NDA Strategy Document

We are in the process of revising
the Strategy that was approved by
Government in 2006:

PDF Strategy (approved by Government 2006) (3Mb)

We will be launching our Draft Strategy II
for consultation in August 2010. 

Click here for more information on Draft Strategy II

Find more documents in our comprehensive Document Library.

.
Home > Our Sites > Hunterston A > Future Plans  

Future Plans

This section provides a brief description of the Hunterston A site as outlined in the NDA's strategy.

The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.


Site End States

 Current plans are all waste to be sent off site for disposal, all buildings to be cleared from the site and the site delicensed, landscaped and available for alternative reuse.

Current Key Milestones

Year

Milestones 

2006  Construction of the ILW store complete
2014  All operational ILW retrieval/processing complete
2017  Entry into care & maintenance stage
2090  Final site clearance and closure