Performance Updates
Find out more about Hinkley Point A's Performance, visit our Programme Performance Updates section.
NDA Strategy Document

After extensive consultation with our stakeholders, Government approved our Strategy published on 30 March 2006
NDA Strategy (pdf)
Find more documents in our comprehensive Document Library.
This section provides a brief description of the Hinkley Point site as outlined in the NDA's strategy.
The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.
Site End State
| Current plans are for the site to be delicensed. |
| Year | Milestones |
|---|---|
| 2012 | Complete decommissioning and backfill of Turbine Hall |
| 2013 | Complete decommissioning of Magnox vault |
| 2016 | Complete processing of historic ILW |
| 2017 | Start of safestore care & maintenance |
| 2095 | Reactor buildings decommissioning complete |
| 2104 | Final site clearance and closure |