This section provides a brief description of the Harwell site as outlined in the NDA's strategy.
The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.
Site End State
| Land will be delicensed when clean-up is complete and released for redevelopment for science, technology and innovation uses as part of the Harwell Science and Innovation Campus. |
Current Key Milestones
| Year | Milestones |
|---|---|
| 2006 | Eastern area of site restored |
| 2010 | Liquid effluent treatment plant discharge to River Thames ceased |
| 2015 | Building B462 waste stores complex - remote handled intermediate level waste (RHILW) operations complete |
| 2016 | Liquid effluent treatment plant remediated |
| 2017 | Building B459 active handling facility - decommissioning complete |
| 2020 | Building B220 radiochemistry facility - decommissioning complete |
| 2022 | Reactors - decommissioning complete |
| 2025 | Final designated site clearance |