Future Plans

Location

Dungeness Location

Performance Updates

Find out more about Dungeness A's Performance, visit our Programme Performance Updates section.

See also

NDA Strategy Document

NDA Strategy Document

After extensive consultation with our stakeholders, Government approved our Strategy published on 30 March 2006

NDA Strategy (pdf)

Find more documents in our comprehensive Document Library.

.
Home > Our Sites > Dungeness A > Future Plans  

Future Plans

This section provides a brief description of the Dungeness A site as outlined in the NDA's strategy.

The scope, schedule and cost of work needed to decommission the sites are reviewed annually by the NDA and its contractors during the Lifetime Plan (LTP) review process.


Site End State
Current plans are for the site to be decommissioned, cleared and landscaped to return back to the shingle foreland by 2111.

Current Key Milestones

 Year

Milestones 

 2006 Generation ceases - both reactors shut down
 2009 Defuelling completed - removal of vast majority of radioactive inventory from site
 2010 Demolish Turbine Hall - Turbine Hall removed to free the land for other decommissioning facilities
 2014 Completion of ILW Store - new waste processing plant erected in place of the Turbine Hall
 2021 Care and maintenance begins - all plant and buildings except reactor containment will have been removed
 2103 Remove ILW Store - ILW store removed ready for final site clearance
 2111 Final site clearance and closure