No pages meet the criteria

Location

Dounreay Location

Web Updates

Keep informed with the latest news and developments from the NDA

Performance Updates

Find out more about Dounreay's Performance, visit our Programme Performance Updates section.

See also

Related Documents

Site Progress Key

On target
On target
Behind target with possibility of recovery
Behind target with possibility of recovery
Behind target
Behind target

Safety and Environmental Performance Key

Nuclear Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more INES Level 1 or above in the month
Industrial Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more RIDDOR reportable events in the month
Environmental Safety
No incidents this month No incidents in the month
One or more incidents in the month One or more environmental non compliances in the month
.
Home > Our Sites > Dounreay  

Dounreay

 Dounreay (© Nuclear Decommissioning Authority 2010. Some images courtesy of site licence companies. Every effort is taken to ensure the accuracy of material or images produced or used by the NDA. However, the NDA cannot guarantee that the images shown will always be current, accurate or complete and does not warrant or endorse the accuracy or completeness of the images.)

Dounreay
Thurso
Caithness
KW14 7TZ

Tel. 01847 802121

Dounreay is located in Caithness, Scotland and has a total site area of 74 hectares. It was established in the mid-1950s as a research reactor site with fuel production and processing facilities. There were three reactors, the last of which ceased operation in 1994.

Dounreay Site Restoration Ltd (DSRL) is the Site Licence Company (SLC) that manages and operates, on behalf of the NDA, Dounreay site. We competed a contract for a Parent Body Organisation (PBO) to provide the vision for the optimal accomplishment of Dounreay site's mission. On 2 April 2012, Babcock Dounreay Partnership, comprising Babcock Nuclear Services Ltd,  CH2M Hill International Nuclear Services Ltd and URS International Holdings (UK) Ltd, were awarded the contract. This  PBO has seconded key personnel to form the SLC's senior leadership team to deliver that vision, driving to attain best value for money while maintaining mandatory standards of safety, security and environmental performance. 

Overview

Age Operated from 1950s - 1994
Site Licensee Dounreay Site Restoration Ltd
Parent Body Organisation Babcock Dounreay Partnership
Status Decommissioning and Termination
Cost - Lifetime
(total discounted* nuclear liability)
£2,471 million

 * The costs of discharging the nuclear liability will be incurred over a significant period of time. To take account of the time value of money, the costs are "discounted" back to a present value. Effectively this is the amount that would need to be invested today, at a set rate of interest (the discount rate) in order to pay for the liability in the future as it falls due.

 

Year Key Activities
2039 Interim State achieved
2034 PFR facility decommissioning complete
2032 All ILW removed from shaft
2029 All NaK residues removed from DFR
2014 LLW facilities commence operations
2012 Bulk NaK destruction complete
2010 Major hazard eliminated
2009 'Reactorsauraus' to tear Dounreay apart
2009 Dounreay says goodbye to largest hazard
2008 Shaft clean-up nominated for top award
2006 An innovative approach to isolate the Dounreay Shaft

 


Progress against this year's targets

Status as at end of financial year 2012/13 (Progress against Quarter 1 of 2012/13 will be reported in July 2013)


Site Restoration

Target Status Commentary

Continue removal of spent fuel cans stored in the PFR buffer store

On target

2012/13 target complete

Ongoing destruction of alkali metal on sodium wetted components from reactor decommissioning

On target

2012/13 target complete

Spent Fuels

Target Status Commentary

Complete preparations and commence 'Out of Reactor' breeder fuel shipments to Sellafield

On target

2012/13 target complete

Complete the removal of fuel from PFR Reprocessing Plant

On target

2012/13 target complete

 

Integrated Waste Management

Target Status Commentary

Continue with the construction of the new LLW Facility

On target

2012/13 target complete

Critical Enablers

Target Status Commentary

Complete inactive commissioning of equipment to remove breeder fuel from the DFR

On target

2012/13 target complete

Complete the design for an Un-irradiated Fuels Characterisation Facility to assay and package un-irradiated fuels for final disposition

On target

2012/13 target complete

Complete the new PBO baseline update to reflect the winning decommissioning strategy

On target

2012/13 target complete

Implementation of the socio-economic and stakeholder engagement plans

On target

2012/13 target complete

 


Safety and Environmental Performance

Status as at end of financial year 2012/13 (Progress against Quarter 1 of 2012/13 will be reported in July 2013)

Nuclear Safety
Industrial Safety
Environmental Safety