Performance Updates
Find out more about Capenhurst's Performance, visit our Programme Performance Updates section.
See also
Related Documents
Parent Company Agreement in respect of Capenhurst Site Part 1
(1.73mb)
Parent Company Agreement in respect of Capenhurst Site Part 2
(1.24mb)
Capenhurst Site Commercial Status Map
(243kb)
Strategic Environmental Assessment - Response to Consultation on the Scoping Report November 2008
(3.07mb)
Find more documents in our comprehensive Document Library.
Site Progress Key
On target |
On target |
Behind target with possibility of recovery |
Behind target with possibility of recovery |
Behind target |
Behind target |
Safety and Environmental Performance Key
| Nuclear Safety | |
|---|---|
|
|
No incidents in the month |
|
|
One or more INES Level 1 or above in the month |
| Industrial Safety | |
|
|
No incidents in the month |
|
|
One or more RIDDOR reportable events in the month |
| Environmental Safety |
|
|
|
No incidents in the month |
|
|
One or more environmental non compliances in the month |
Capenhurst
Capenhurst
Sellafield Sites
Chester
Cheshire
CH1 6ER
Tel. 0151 3394101
Capenhurst is located near Ellesmere Port in Cheshire, adjacent to Urenco (the Uranium Enrichment Company), and has an area of 32 hectares covered by the nuclear site licence. It was home to a uranium enrichment plant and associated facilities that ceased operation in 1982.
|
Location |
Ellesmere Port, Cheshire |
|---|---|
|
Age |
Operated from 1953 - 1982 |
|
Site Licensee |
Sellafield Limited |
|
Status |
Decommissioning and Termination |
Progress against this year's targets
Status as at end Quarter 3 (end December 2011) - next update due April 2012
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Prioritisation of funding for high risk and hazard legacy wastes |
On target |
On track |
Nuclear Materials
| Target | Status | Commentary |
|---|---|---|
Review the business case for potential consolidations of nuclear materials |
On target |
On track |
Support Government policy development for plutonium options |
On target |
Complete. Preferred options paper delivered on schedule in June 2011. |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Provide programme cohesive overview of the Magnox Operating Programme (MOP) |
On target |
On track |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Drive adoption and implementation of the Low Level Waste (LLW) Strategy (ACCELS) |
On target |
On track - Note: The title ACCELS has now been dropped and we are now just referencing to this as our National Programme for implementation of the UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry (published August 2010) |
Business Optimisation
| Target | Status | Commentary |
|---|---|---|
Secure a future for Capenhurst that maximises overall value for money |
On target |
Complete |
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Combined development of Skills and People Strategy |
On target |
On track |
Continue development of effective stakeholder engagement |
On target |
On track |
Embed the new ways of working in the NDA and estate following the Organisational Review |
On target |
On track |
Embed the updated Strategy |
On target |
On track |
Ensure delivery of 10% support and overhead cost reductions |
On target |
On track |
Extend contracts through to completion of competition for Magnox and RSRL |
On target |
On track |
Complete new Parent Body (PBO) contract award for Dounreay |
On target |
On track |
Review delivery of NDA's socio-economic obligations |
On target |
On track |
Review National Nuclear Archive project in line with NDA Information and Knowledge Management Strategy |
On target |
On track |