Forthcoming Events

13 September 2010
Research workshop on geological disposal challenge
EPSRC, under the auspices of the Research Councils Energy Programme (RCEP), has been working with NDA to identify relevant research challenges associated with the implementation of a geological waste facility.

21 September 2010
11th National Stakeholder Group Meeting
This meeting is by invitation only. It allowed declared stakeholders to engage with NDA on various issues of national interest.

22 September 2010
Socio Economic Panel
Panel to consider funding requests under £100,000.

Press Enquiries

For urgent enquiries out of office hours, please use the mobile phone numbers below:

Bill Hamilton
Head of Stakeholder
Communications

Office: 01925 802193
Mobile: 07816 315132

Brian Hough
Communications Manager

Office: 01925 802177
Mobile: 07812 554009

Rachael Collins
Communications Manager

Office: 01925 802255
Mobile: 07971 918968

Deborah Ward
Communications Manager

Office: 01925 802343 
Mobile: 07980 930838

Web Updates

Keep informed with the latest news and developments from the NDA

Related News

01 September 2010
Next phase in our Strategy for Consultation
Today we have published the draft of our updated Strategy for consultation.

12 May 2010
Sellafield MOX Plant (SMP) Future
Commercial arrangements secured to continue to improve performance of SMP in the longer term to ensure customer expectations are met.

29 March 2010
New operational arrangements at Springfields
Westinghouse and NDA mark the start of new operational arrangements for UK fuel manufacturing site.

24 March 2010
Springfields agreement secures site future
The NDA has now concluded an agreement with Westinghouse Electric Company that will secure the future of the Springfields nuclear facility in Preston.

10 September 2009
Advanced discussion over future for Springfields
NDA to explore possibilities for extracting greater value from Springfields than was previously envisaged.

Find more News Items

.


.
Home > News and Events > Sellafield MOX Plant Update  

Sellafield MOX Plant Update

16 February 2006

The SMP plant manufactures fuel from Plutonium, separated from spent fuel in the THORP reprocessing facility, and natural or depleted uranium. The overall process efficiency is around 98%, due to the internal recycle capability within the plant.

The SMP plant is continuing active commissioning and is in the early stages of ramp up, as such the manufacturing processes are not yet mature. It is producing fuel of a good quality with early production fuel performing well in reactor.

For SMP to generate a positive economic impact, customer contracts must obviously be secured and delivered and to do this a ramp up of production capacity must be achieved over time with an ultimate target of around 40 te HM/yr. Ongoing assessments will determine the ramp up rates required.

The production plan for this year was to increase the number of fabricated assemblies by 300%. The plant has experienced a number of equipment reliability problems and some engineering programme slippage which have limited the production which is likely to be achieved this year. It is now believed that, this financial year, two thirds of the planned output will be achieved with the balance being fabricated in the early summer of 06.

As part of a comprehensive improvement programme, a detailed modelling analysis of the plant production capability for each anticipated fuel type has now been completed. For the types of fuel that are scheduled to be produced in the next few years this analysis shows that the plant production rate is likely to be around 80% of that which was planned for the LCBL2. For fuel types anticipated in future years the achievement of LCBL2 rates looks unlikely if improvements, in addition to those already planned, are not implemented.

As a result of the modelling work, packages are being executed which assess further engineering improvement opportunities and optimisation of the production schedule.

Progress has been made in addressing recent bottleneck areas. The detailed model is being used to identify future plant constraints and to target further production rate enhancement projects. It is intended that this work will be completed in the summer.

The production programme is being optimised to maximise the capability of the plant whilst minimising any impact on customer commitments. In addition the results of the modelling and potential requirements for a longer plant life are being fed into the economic model to assess the impact.

Conclusion

Although the production achieved to date is not as high as planned the expected year end out-turn rate nevertheless represents an increase of more than 100% on last year.

A significant programme of plant capacity and capability improvements is under development aimed at increasing the throughput to levels that will meet customer requirements.

The modelling work indicates that the ramp up is likely to be slower than planned and the programme is currently being examined to determine what other opportunities could be exploited.

Achievement of the original design capacity throughput rate of 120 te HM/yr is not considered feasible.