Forthcoming Events
17 March 2010
10th National Stakeholder Group Meeting
This meeting is by invitation only. It allows declared stakeholders to engage with NDA on various issues of national interest.
17 March 2010
Demo: Lasers in Nuclear Decommissioning
TWI Ltd present a NDA funded project to demonstrate the capabilities of lasers for surface removal of contaminated concrete and cutting of pipe and metalwork.
05 May 2010
Socio Economic Panel
Panel to consider funding requests under £100,000.
Press Enquiries
For urgent enquiries out of office hours, please use the mobile phone numbers below:
Bill Hamilton
Head of Stakeholder
Communications
Office: 01925 802193
Mobile: 07816 315132
Brian Hough
Communications Manager
Office: 01925 802177
Mobile: 07812 554009
Rachael Collins
Communications Manager
Office: 01925 802255
Mobile: 07971 918968
Deborah Ward
Communications Manager
Office: 01925 802343
Mobile: 07980 930838
Web Updates
Narrow or Expand Results
Related News
10 September 2009
Advanced discussion over future for Springfields
NDA to explore possibilities for extracting greater value from Springfields than was previously envisaged.
04 August 2009
Land disposal process moves to next phase
Opportunity to express interest in taking part in the disposal of land adjacent to Sellafield, Cumbria, has closed.
09 June 2009
Wylfa meets first goal in generation
Wylfa Power Station, North Wales, granted approval to continue generating electricity past its planned closure date of March 2010.
08 June 2009
Land disposal process at Sellafield launched
NDA announces the start of the disposal process for land adjacent to the nuclear site at Sellafield in Cumbria.
01 June 2009
Oldbury return to full power
NDA's Oldbury Power Station is celebrating its return to generating electricity at ‘full-power’ after five years of reduced output.
Sellafield MOX Plant Update
16 February 2006
The SMP plant manufactures fuel from Plutonium, separated from spent fuel in the THORP reprocessing facility, and natural or depleted uranium. The overall process efficiency is around 98%, due to the internal recycle capability within the plant.
The SMP plant is continuing active commissioning and is in the early stages of ramp up, as such the manufacturing processes are not yet mature. It is producing fuel of a good quality with early production fuel performing well in reactor.
For SMP to generate a positive economic impact, customer contracts must obviously be secured and delivered and to do this a ramp up of production capacity must be achieved over time with an ultimate target of around 40 te HM/yr. Ongoing assessments will determine the ramp up rates required.
The production plan for this year was to increase the number of fabricated assemblies by 300%. The plant has experienced a number of equipment reliability problems and some engineering programme slippage which have limited the production which is likely to be achieved this year. It is now believed that, this financial year, two thirds of the planned output will be achieved with the balance being fabricated in the early summer of 06.
As part of a comprehensive improvement programme, a detailed modelling analysis of the plant production capability for each anticipated fuel type has now been completed. For the types of fuel that are scheduled to be produced in the next few years this analysis shows that the plant production rate is likely to be around 80% of that which was planned for the LCBL2. For fuel types anticipated in future years the achievement of LCBL2 rates looks unlikely if improvements, in addition to those already planned, are not implemented.
As a result of the modelling work, packages are being executed which assess further engineering improvement opportunities and optimisation of the production schedule.
Progress has been made in addressing recent bottleneck areas. The detailed model is being used to identify future plant constraints and to target further production rate enhancement projects. It is intended that this work will be completed in the summer.
The production programme is being optimised to maximise the capability of the plant whilst minimising any impact on customer commitments. In addition the results of the modelling and potential requirements for a longer plant life are being fed into the economic model to assess the impact.
Conclusion
Although the production achieved to date is not as high as planned the expected year end out-turn rate nevertheless represents an increase of more than 100% on last year.
A significant programme of plant capacity and capability improvements is under development aimed at increasing the throughput to levels that will meet customer requirements.
The modelling work indicates that the ramp up is likely to be slower than planned and the programme is currently being examined to determine what other opportunities could be exploited.
Achievement of the original design capacity throughput rate of 120 te HM/yr is not considered feasible.