Forthcoming Events

Press Enquiries

For urgent enquiries out of office hours, please use the mobile phone numbers below:

National

Bill Hamilton
Head of Stakeholder
Relations
Office: 01925 802193
Mobile: 07816 315132

Deborah Ward
Corporate Communications
Manager
Office: 01925 802343
Mobile: 07980 930838 

Cumbria

Brian Hough
Stakeholder Relations
Manager - Cumbria

Office: 01925 802177
Mobile: 07812 554009

Dounreay

Anna MacConnell
Stakeholder Relations
Manager - Caithness
Office: 01925 802497
Mobile: 07889 117204 

Other Sites

Jonathan Jenkin
Stakeholder Relations
Manager - Magnox
Office: 01925 802345
Mobile: 07970 746313 

Web Updates

Keep informed with the latest news and developments from the NDA

See also

No pages meet the criteria

Web Updates

Keep informed with the latest news and developments from the NDA

.
Home > News and Events > Asbestos removal milestone met at Calder Hall  

Asbestos removal milestone met at Calder Hall

24 March 2010

 Calder Hall Reactor 4 after asbestos was stripped

The latest decommissioning milestone for Calder Hall has been achieved with the removal of 2300 tonnes of asbestos cladding. The five year project to strip asbestos cladding from the heat exchangers, turbine halls and associated plant was completed this work. It was the culmination of one million man hours of work. Alongside a similar project at Chapelcross, the asbestos strip is reckoned to be the largest in Europe.

Ian Hudson, the NDA's Programme Director for Sellafield Site Facing Team said:

"This is an excellent achievement for the Calder Hall team. The asbestos removal is a major step forward in the overall decommissioning programme and the success of this project demonstrates how hazards can be effectively reduced through well managed, safe operations." 

Since Calder Hall ceased electricity production in 2003, the asbestos was no longer kept at a constant temperature and its stability couldn't be guaranteed. Therefore, a method of safely removing the asbestos in line with strict regulations was piloted and a contractor engaged. Estimated to cost £27.58m, the project's actual end cost was £26.25m, a saving of some £1.33m.

Stuart MacVean, Spent Fuel Management Director, Sellafield Ltd added: "We are working very hard to accelerate the clean-up and remediation work at Sellafield and the fact that this project has been successfully completed on time and within budget demonstrates our total commitment to the job. The £1m saving is exactly the type of efficiency we are looking to replicate in other projects."

Not only did the project involve working with a known carcinogen, but much of the work was also carried out at height. Scaffold towers over 36m tall had to be built around the sixteen heat exchangers on the outside of the reactors. These formed the structure for asbestos tents which prevented the release of asbestos and ensured ventilation for the workers. Around 100 individuals worked in arduous and confined conditions. At no time were any workers exposed to asbestos because of safe working practices and strict adherence to regulations.