On target |
On target |
Behind target with possibility of recovery |
Behind target with possibility of recovery |
Behind target |
Behind target |
Site Safety and Environmental Performance

Find out more about NDA Sites' Performance, visit our Site Safety and Environmental Performance section.
Progress against this year's targets
Our current Business Plan outlines what we intend to achieve this year. In summary this includes
- delivering and accelerating the work on the Legacy Ponds and Silos at Sellafield
- working towards taking the Dounreay site to its Interim State
- optimising route towards Care and Maintenance across the Magnox fleet and at Harwell and Winfrith
- dealing with the loss of income arising from the end of power generation at Oldbury
- the implementation of the Low Level Waste strategy at the Low Level Waste Repository (LLWR)
Specific targets sit behind this planned activity. Progress against these business plan targets is outlined below.
NDA Business Plan 2012 - 2015 (1Mb)
The status of progress against targets outlined below is based on reporting at the end of Quarter 3 (end December 2012).
Status as at end of Quarter 3 of 2012/13 (Progress against Quarter 4 will be reported in May 2013)
Sellafield
Site Restoration
| Target | Status | Commentary |
|---|---|---|
First Generation Magnox Storage Pond - Commence retrieval of fuel from pond floor |
On target |
2012/13 target complete |
Pile Fuel Cladding Silo Programme - Complete construction of the superstructure to house the equipment needed to retrieve waste from the silo |
On target |
2012/13 target complete |
Pile Fuel Cladding Silo Programme - Complete Retrievals Access Penetration detailed design |
On target |
2012/13 target complete |
Pile Fuel Storage Pond - Continue removal of sludge from the pond |
On target |
2012/13 target complete |
Pile Fuel Storage Pond - Continue removal of contaminated metal for treatment and storage |
On target |
2012/13 target complete |
Pile Fuel Storage Pond - Continue the transfer of metal from the pond for storage |
On target |
2012/13 target complete |
Pile Fuel Storage Pond - Commence the transfer of oxide fuel from the pond for storage |
On target |
2012/13 target complete |
Magnox Swarf Storage Silo - Complete ‘project concept’ design review for Silos Direct Encapsulation Plant |
On target |
2012/13 target complete |
Magnox Swarf Storage Silo - Complete the Silo Emptying Plant assembly |
On target |
2012/13 target complete |
Capenhurst - Progress site integration into URENCO |
On target |
2012/13 target complete |
Capenhurst - Continue to process uranic residues |
On target |
2012/13 target complete |
First Generation Magnox Storage Pond - Complete construction of Sludge Packaging Plant 1 buffer storage facility |
Behind target |
Target for 2012/13 has not been met |
Magnox Swarf Storage Silo - Complete seismic improvements on second extension |
Behind target |
Target for 2012/13 has not been met |
Decommissioning - Progress removal of filter gallery from Windscale Chimney Pile 1 |
Behind target |
Target for 2012/13 has not been met |
Decommissioning - Continue to retrieve and treat, for long-term storage, legacy flocculent from the flocculent storage tanks |
Behind target |
Target for 2012/13 has not been met |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
AGR Programme – ongoing removal of Multi-Element Bottles (MEBs) from THORP |
On target |
2012/13 target complete |
Receive the first batch of Dounreay Fast Reactor (DFR) Breeder fuel at Sellafield |
On target |
2012/13 target complete
|
Continue to receive Advanced Gas Reactor (AGR) fuel from EDF |
On target |
2012/13 target complete
|
Continue to reprocess Magnox Fuel in line with the Magnox Operating Programme |
Behind target |
Target for 2012/13 has not been met
|
Continue to reprocess oxide fuel through Thermal Oxide Reprocessing Plant (THORP) from EDF and overseas customers |
Behind target |
Target for 2012/13 has not been met |
Nuclear Materials
| Target | Status | Commentary |
|---|---|---|
Sellafield is the custodian of the majority of the UK's stock of plutonium and its safe secure storage is of the utmost priority. Consolidation of materials is an ongoing activity and will continue to be part of the sites mission. |
On target |
2012/13 target complete |
Continue the safe and secure storage of plutonium in line with UK policy |
On target |
2012/13 target complete |
Explore the consolidation of materials across the NDA estate |
On target |
2012/13 target complete |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Continue to repatriate overseas owned vitrified HAL to country of origin |
On target |
2012/13 target complete |
Continue to transfer legacy Plutonium Contaminated Material (PCM) to modern engineered stores |
On target |
2012/13 target complete |
Diversion of materials from LLWR in line with the LLW Strategy implementation and optimisation |
On target |
2012/13 target complete |
Continue to receive further module deliveries for the construction of Evaporator D |
On target |
2012/13 target complete |
Continue to process HAL through the Waste Vitrification Plant |
Behind target |
Target for 2012/13 has not been met |
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Complete handover of refurbished Grid Transfers |
On target |
2012/13 target complete |
Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up |
On target |
2012/13 target complete |
Complete handover of the boiler park from Sellafield to Fellside |
Behind target |
Target for 2012/13 has not been met |
Continue the Sellafield infrastructure enhancement programme |
Behind target |
Target for 2012/13 has not been met |
Implementation of the focus areas of the Integrated Change Programme (ICP) across all operating units |
Behind target |
Target for 2012/13 has not been met |
Across Magnox Ltd
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Management of the Magnox Operating Programme (MOP) and co-ordination of Magnox fuel management activities with Sellafield and Dounreay |
Behind target |
Spent Fuel deliveries 359 teU. Overall stocks of wetted Magnox fuel managed for Sellafield shutdowns in 2013/14. Overall spent fuel delivery capability for 2012/13 was 890 teU |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Delivery of the Magnox and LLWR joint waste management plan for LLW |
Behind target |
All targets met or exceeded (4/5) with the exception of the VLLW component |
Business Optimisation
| Target | Status | Commentary |
|---|---|---|
Seek to optimise electricity generation at Wylfa |
On target |
2012/13 target complete |
Explore synergies of new build activities adjacent to NDA sites through utilisation of existing assets where appropriate to reduce impact and costs |
On target |
2012/13 target complete |
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Provide support to the NDA in competition for the PBO |
On target |
2012/13 target complete |
Execute and continuously improve delivery of the Magnox Optimised Decommissioning Programme (MODP) |
On target |
2012/13 target complete |
Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up |
On target |
2012/13 target complete |
Establish the 'lead and learn' principle and focus on building a delivery organisation. |
On target |
2012/13 target complete
|
Embed a Programme Delivery Organisation across the Magnox estate and drive value through implementation of best practice |
On target |
2012/13 target complete
|
Berkeley
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Continue active waste vaults retrieval |
On target |
2012/13 target complete |
Continue retrieval and packaging of other ILW wastes |
On target |
2012/13 target complete |
Bradwell
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Continued pilecap de-plant |
On target |
2012/13 target complete |
Ponds centre bay drained and stabilised |
On target |
2012/13 target complete |
Dessicant retrieval complete |
On target |
2012/13 target complete |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Complete active commissioning of aqueous discharge abatement plant |
Behind target |
The revised schedule indicates plant will not be complete to meet this target due to design and manufacturing delays. This will not stop the site entering Care & Maintenance as planned. |
Commence FED retrieval and dissolution |
Behind target |
The target dates for both FED targets were very challenging and have been missed. Progress on construction progressing to a July 2013 completion.
|
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Capture lessons learned for application to other Magnox sites (lead and learn) |
On target |
2012/13 target complete
|
Chapelcross
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Completion of bulk asbestos removal from heat exchangers and turbine hall |
On target |
2012/13 target complete |
Continued hazard reduction activities towards interim Care and Maintenance
|
On target |
Appropriate activities are being discharged |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Completion of reactor defuelling requirements in line with Magnox Operating Programme (MOP) |
On target |
2012/13 target complete |
Dungeness A
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Continued hazard reduction activities towards interim Care and Maintenance |
On target |
Appropriate activities are being discharged |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Completion of reactor defuelling requirements in line with Magnox Operating Programme (MOP) |
On target |
2012/13 target complete |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Complete retrieval and processing of Low Level Waste (LLW) sludge |
On target |
2012/13 target complete |
Hinkley Point A
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Complete bulk asbestos removal |
On target |
2012/13 target complete |
Hunterston A
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Pond dewatering and drainage ongoing |
On target |
2012/13 target complete |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Continued development and optimisation of solid ILW Management programme |
On target |
2012/13 target complete |
Oldbury
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Preparations for decommissioning hazard reduction |
On target |
2012/13 target complete |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Commencement of reactor defuelling in line with Magnox Operating Programme (MOP) |
On target |
2012/13 target complete |
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Commencement of the organisational change programme for decommissioning |
On target |
Appropriate activities are being discharged |
Sizewell A
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Maintain facilities in a safe state |
On target |
Appropriate activities are being discharged |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Continue defuelling in line with Magnox Operating Programme (MOP) |
On target |
2012/13 target complete |
Trawsfynydd
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Continue safe-store asset care activities to support Care and Maintenance entry |
On target |
2012/13 target complete |
Complete the strengthening of the capping roof |
On target |
2012/13 target complete |
Complete North Lane Pond scabbling |
Behind target |
Final pass suspended due to optioneering to establish best practical end state. |
Completion of North FED civil enabling works |
Behind target |
Ventilation issues and unexpected contamination screed layer. Completion expected mid May 2013. |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Complete transfer of legacy waste to the Intermediate Level Waste (ILW) store |
On target |
2012/13 target complete |
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Capture lessons learned for application to other Magnox sites (lead and learn) |
On target |
2012/13 target complete |
Review the opportunity for personnel and skills transfer between Trawsfynydd, Wylfa and potential new build on Anglesey |
On target |
Appropriate activities are being discharged |
Wylfa
Business Optimisation
| Target | Status | Commentary |
|---|---|---|
Explore the opportunity for continued electricity generation beyond December 2012 |
On target |
2012/13 target complete |
Dounreay
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Ongoing destruction of alkali metal on sodium wetted components from reactor decommissioning |
On target |
2012/13 target complete |
Continue removal of spent fuel cans stored in the PFR buffer store |
On target |
2012/13 target complete |
Spent Fuels
| Target | Status | Commentary |
|---|---|---|
Complete preparations and commence 'Out of Reactor' breeder fuel shipments to Sellafield |
On target |
2012/13 target complete |
Complete the removal of fuel from PFR Reprocessing Plant |
On target |
2012/13 target complete
|
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Continue with the construction of the new LLW Facility |
On target |
2012/13 target complete |
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Complete inactive commissioning of equipment to remove breeder fuel from the DFR |
On target |
2012/13 target complete |
Complete the new PBO baseline update to reflect the winning decommissioning strategy |
On target |
2012/13 target complete |
Complete the design for an Un-irradiated Fuels Characterisation Facility to assay and package un-irradiated fuels for final disposition |
On target |
2012/13 target complete |
Implementation of the socio-economic and stakeholder engagement plans |
On target |
2012/13 target complete
|
Across Research Site Restoration Ltd
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Development of programme optimisation including accelerated scenarios/options |
On target |
2012/13 target complete
|
Critical Enablers
| Target | Status | Commentary |
|---|---|---|
Provide support to the NDA in the competition for a new Parent Body Organisation (PBO) |
On target |
2012/13 target complete |
Development of optimised decommissioning plan options |
On target |
2012/13 target complete
|
Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up |
On target |
2012/13 target complete
|
Harwell
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Care and Maintenance of redundant reactors and other facilities |
On target |
2012/13 target complete |
Decommissioning of Liquid Effluent Treatment Plant (LETP) |
Behind target |
Target for 2012/13 missed |
Nuclear Materials
| Target | Status | Commentary |
|---|---|---|
Progress the capability to transfer materials off site |
On target |
2012/13 target complete |
Integrated Waste Management
| Target | Status | Commentary |
|---|---|---|
Recovery, processing and packaging of solid ILW |
On target |
2012/13 target complete
|
Winfrith
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Prepare Winfrith for Interim State in a safe and secure manner and review opportunities for optimisation |
On target |
2012/13 target complete |
LLWR
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Commence site preparation for phased construction of final cap |
On target |
12/13 Target Complete |
Ongoing implementation of the Environmental Safety Case |
On target |
12/13 Target Complete |
Ongoing decommissioning of PCM facilities |
Behind target |
Milestones have been completed but late to schedule due to a change to the delivery strategy during the year |
Springfields
Site Restoration
| Target | Status | Commentary |
|---|---|---|
Continue the Post Operational Clean Out (POCO) and decommissioning of redundant areas |
On target |
2012/13 target complete |
Nuclear Materials
| Target | Status | Commentary |
|---|---|---|
Processing historic residues to recover uranium to return to the nuclear fuel cycle.
|
On target |
2012/13 target complete |