2011/12 targets - final report
Site Safety Performance Updates

Site Progress Key

On target
On target
Behind target with possibility of recovery
Behind target with possibility of recovery
Behind target
Behind target

Site Safety and Environmental Performance

Site Safety updates

Find out more about NDA Sites' Performance, visit our Site Safety and Environmental Performance section.

.
Home > About NDA > Progress against this year's targets  

Progress against this year's targets  

Business Plan 2012-2015 front cover

Our current Business Plan outlines what we intend to achieve this year. In summary this includes

  • delivering and accelerating the work on the Legacy Ponds and Silos at Sellafield
  • working towards taking the Dounreay site to its Interim State
  • optimising route towards Care and Maintenance across the Magnox fleet and at Harwell and Winfrith
  • dealing with the loss of income arising from the end of power generation at Oldbury
  • the implementation of the Low Level Waste strategy at the Low Level Waste Repository (LLWR)

Specific targets sit behind this planned activity. Progress against these business plan targets is outlined below.

PDF NDA Business Plan 2012 - 2015 (1Mb)

The status of progress against targets outlined below is based on reporting at the end of Quarter 3 (end December 2012).

 


Status as at end of Quarter 3 of 2012/13 (Progress against Quarter 4 will be reported in May 2013)

Sellafield

Sellafield

Site Restoration

Target Status Commentary

First Generation Magnox Storage Pond - Commence retrieval of fuel from pond floor

On target

2012/13 target complete

Pile Fuel Cladding Silo Programme - Complete construction of the superstructure to house the equipment needed to retrieve waste from the silo

On target

2012/13 target complete

Pile Fuel Cladding Silo Programme - Complete Retrievals Access Penetration detailed design

On target

2012/13 target complete

Pile Fuel Storage Pond - Continue removal of sludge from the pond

On target

2012/13 target complete

Pile Fuel Storage Pond - Continue removal of contaminated metal for treatment and storage

On target

2012/13 target complete

Pile Fuel Storage Pond - Continue the transfer of metal from the pond for storage

On target

2012/13 target complete

Pile Fuel Storage Pond - Commence the transfer of oxide fuel from the pond for storage

On target

2012/13 target complete

Magnox Swarf Storage Silo - Complete ‘project concept’ design review for Silos Direct Encapsulation Plant

On target

2012/13 target complete

Magnox Swarf Storage Silo - Complete the Silo Emptying Plant assembly

On target

2012/13 target complete

Capenhurst - Progress site integration into URENCO

On target

2012/13 target complete

Capenhurst - Continue to process uranic residues

On target

2012/13 target complete

First Generation Magnox Storage Pond - Complete construction of Sludge Packaging Plant 1 buffer storage facility

Behind target

Target for 2012/13 has not been met

Magnox Swarf Storage Silo - Complete seismic improvements on second extension

Behind target

Target for 2012/13 has not been met

Decommissioning - Progress removal of filter gallery from Windscale Chimney Pile 1

Behind target

Target for 2012/13 has not been met

Decommissioning - Continue to retrieve and treat, for long-term storage, legacy flocculent from the flocculent storage tanks

Behind target

Target for 2012/13 has not been met

Spent Fuels

Target Status Commentary

AGR Programme – ongoing removal of Multi-Element Bottles (MEBs) from THORP

On target

2012/13 target complete

Receive the first batch of Dounreay Fast Reactor (DFR) Breeder fuel at Sellafield

On target

2012/13 target complete

 

 Continue to receive Advanced Gas Reactor (AGR) fuel from EDF

On target

2012/13 target complete

 

Continue to reprocess Magnox Fuel in line with the Magnox Operating Programme

Behind target

Target for 2012/13 has not been met

 

Continue to reprocess oxide fuel through Thermal Oxide Reprocessing Plant (THORP) from EDF and overseas customers

Behind target
Target for 2012/13 has not been met

Nuclear Materials

Target Status Commentary

Sellafield is the custodian of the majority of the UK's stock of plutonium and its safe secure storage is of the utmost priority. Consolidation of materials is an ongoing activity and will continue to be part of the sites mission.

On target

2012/13 target complete

Continue the safe and secure storage of plutonium in line with UK policy

On target

2012/13 target complete

Explore the consolidation of materials across the NDA estate

On target

2012/13 target complete

Integrated Waste Management

Target Status Commentary

Continue to repatriate overseas owned vitrified HAL to country of origin

On target

2012/13 target complete

Continue to transfer legacy Plutonium Contaminated Material (PCM) to modern engineered stores

On target

2012/13 target complete

 Diversion of materials from LLWR in line with the LLW Strategy implementation and optimisation

On target

2012/13 target complete

Continue to receive further module deliveries for the construction of Evaporator D

On target

2012/13 target complete

Continue to process HAL through the Waste Vitrification Plant

Behind target

Target for 2012/13 has not been met

Critical Enablers

Target Status Commentary

Complete handover of refurbished Grid Transfers

On target

2012/13 target complete

Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up

On target

2012/13 target complete

 Complete handover of the boiler park from Sellafield to Fellside

Behind target

Target for 2012/13 has not been met

Continue the Sellafield infrastructure enhancement programme

Behind target

Target for 2012/13 has not been met

Implementation of the focus areas of the Integrated Change Programme (ICP) across all operating units

Behind target

Target for 2012/13 has not been met

Magnox

Across Magnox Ltd

Spent Fuels

Target Status Commentary

Management of the Magnox Operating Programme (MOP) and co-ordination of Magnox fuel management activities with Sellafield and Dounreay

Behind target

Spent Fuel deliveries 359 teU.  Overall stocks of wetted Magnox fuel managed for Sellafield shutdowns in 2013/14.  Overall spent fuel delivery capability for 2012/13 was 890 teU

Integrated Waste Management

Target Status Commentary

Delivery of the Magnox and LLWR joint waste management plan for LLW

Behind target

All targets met or exceeded (4/5) with the exception of the VLLW component

Business Optimisation

Target Status Commentary

Seek to optimise electricity generation at Wylfa

On target

2012/13 target complete

Explore synergies of new build activities adjacent to NDA sites through utilisation of existing assets where appropriate to reduce impact and costs

On target

2012/13 target complete

Critical Enablers

Target Status Commentary

Provide support to the NDA in competition for the PBO

On target

2012/13 target complete

Execute and continuously improve delivery of the Magnox Optimised Decommissioning Programme (MODP)

On target

2012/13 target complete

Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up

On target

2012/13 target complete

Establish the 'lead and learn' principle and focus on building a delivery organisation.

On target

2012/13 target complete

 

Embed a Programme Delivery Organisation across the Magnox estate and drive value through implementation of best practice

On target

2012/13 target complete

 

Berkeley

Integrated Waste Management

Target Status Commentary

Continue active waste vaults retrieval

On target

2012/13 target complete

Continue retrieval and packaging of other ILW wastes

On target

2012/13 target complete

Bradwell

Site Restoration

Target Status Commentary

Continued pilecap de-plant

On target

2012/13 target complete

Ponds centre bay drained and stabilised

On target

2012/13 target complete

Dessicant retrieval complete

On target

2012/13 target complete

Integrated Waste Management

Target Status Commentary

Complete active commissioning of aqueous discharge abatement plant

Behind target

The revised schedule indicates plant will not be complete to meet this target due to design and manufacturing delays. This will not stop the site entering Care & Maintenance as planned.

Commence FED retrieval and dissolution

Behind target

The target dates  for both FED targets were very challenging and have been missed.  Progress on construction progressing to a July 2013 completion.

 

Critical Enablers

Target Status Commentary

Capture lessons learned for application to other Magnox sites (lead and learn)

On target

2012/13 target complete

 

Chapelcross

Site Restoration

Target Status Commentary

Completion of bulk asbestos removal from heat exchangers and turbine hall

On target

2012/13 target complete

Continued hazard reduction activities towards interim Care and Maintenance

 

On target

Appropriate activities are being discharged

Spent Fuels

Target Status Commentary

Completion of reactor defuelling requirements in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Dungeness A

Site Restoration

Target Status Commentary

 Continued hazard reduction activities towards interim Care and Maintenance

On target

Appropriate activities are being discharged

Spent Fuels

Target Status Commentary

Completion of reactor defuelling requirements in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Integrated Waste Management

Target Status Commentary

Complete retrieval and processing of Low Level Waste (LLW) sludge

On target

2012/13 target complete

Hinkley Point A

Site Restoration

Target Status Commentary

Complete bulk asbestos removal

On target

2012/13 target complete

Hunterston A

Site Restoration

Target Status Commentary

Pond dewatering and drainage ongoing

On target

2012/13 target complete

Integrated Waste Management

Target Status Commentary

Continued development and optimisation of solid ILW Management programme

On target

2012/13 target complete

Oldbury

Site Restoration

Target Status Commentary

Preparations for decommissioning hazard reduction

On target

2012/13 target complete

Spent Fuels

Target Status Commentary

Commencement of reactor defuelling in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Critical Enablers

Target Status Commentary

Commencement of the organisational change programme for decommissioning

On target

Appropriate activities are being discharged

Sizewell A

Site Restoration

Target Status Commentary

Maintain facilities in a safe state

On target

Appropriate activities are being discharged

Spent Fuels

Target Status Commentary

Continue defuelling in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Trawsfynydd

Site Restoration

Target Status Commentary

Continue safe-store asset care activities to support Care and Maintenance entry

On target

2012/13 target complete

Complete the strengthening of the capping roof

On target

2012/13 target complete

Complete North Lane Pond scabbling

Behind target

Final pass suspended due to optioneering to establish best practical end state.

Completion of North FED civil enabling works

Behind target

Ventilation issues and unexpected contamination screed layer.  Completion expected mid May 2013.

Integrated Waste Management

Target Status Commentary

Complete transfer of legacy waste to the Intermediate Level Waste (ILW) store

On target

2012/13 target complete

Critical Enablers

Target Status Commentary

Capture lessons learned for application to other Magnox sites (lead and learn)

On target

2012/13 target complete

Review the opportunity for personnel and skills transfer between Trawsfynydd, Wylfa and potential new build on Anglesey

On target

Appropriate activities are being discharged

Wylfa

Business Optimisation

Target Status Commentary

Explore the opportunity for continued electricity generation beyond December 2012

On target

2012/13 target complete

Dounreay

Dounreay

Site Restoration

Target Status Commentary

Ongoing destruction of alkali metal on sodium wetted components from reactor decommissioning

On target

2012/13 target complete

Continue removal of spent fuel cans stored in the PFR buffer store

On target

2012/13 target complete

Spent Fuels

Target Status Commentary

Complete preparations and commence 'Out of Reactor' breeder fuel shipments to Sellafield

On target

2012/13 target complete

Complete the removal of fuel from PFR Reprocessing Plant

On target

2012/13 target complete

 

Integrated Waste Management

Target Status Commentary

Continue with the construction of the new LLW Facility

On target

2012/13 target complete

Critical Enablers

Target Status Commentary

Complete inactive commissioning of equipment to remove breeder fuel from the DFR

On target

2012/13 target complete

Complete the new PBO baseline update to reflect the winning decommissioning strategy

On target

2012/13 target complete

Complete the design for an Un-irradiated Fuels Characterisation Facility to assay and package un-irradiated fuels for final disposition

On target

2012/13 target complete

Implementation of the socio-economic and stakeholder engagement plans

On target

2012/13 target complete

 

Research

Across Research Site Restoration Ltd

Site Restoration

Target Status Commentary

Development of programme optimisation including accelerated scenarios/options

On target

2012/13 target complete

 

Critical Enablers

Target Status Commentary

Provide support to the NDA in the competition for a new Parent Body Organisation (PBO)

On target

2012/13 target complete

Development of optimised decommissioning plan options

On target

2012/13 target complete

 

Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up

On target

2012/13 target complete

 

Harwell

Site Restoration

Target Status Commentary

Care and Maintenance of redundant reactors and other facilities

On target

2012/13 target complete

Decommissioning of Liquid Effluent Treatment Plant (LETP)

Behind target

Target for 2012/13 missed

Nuclear Materials

Target Status Commentary

Progress the capability to transfer materials off site

On target

2012/13 target complete

Integrated Waste Management

Target Status Commentary

Recovery, processing and packaging of solid ILW

On target

2012/13 target complete

 

Winfrith

Site Restoration

Target Status Commentary

Prepare Winfrith for Interim State in a safe and secure manner and review opportunities for optimisation

On target

2012/13 target complete

LLWR

LLWR

Site Restoration

Target Status Commentary

Commence site preparation for phased construction of final cap

On target

12/13 Target Complete

Ongoing implementation of the Environmental Safety Case

On target

12/13 Target Complete

Ongoing decommissioning of PCM facilities

Behind target

Milestones have been completed but late to schedule due to a change to the delivery strategy during the year

Springfields

Springfields

Site Restoration

Target Status Commentary

 Continue the Post Operational Clean Out (POCO) and decommissioning of redundant areas

On target

2012/13 target complete

Nuclear Materials

Target Status Commentary

Processing historic residues to recover uranium to return to the nuclear fuel cycle.

 

On target

2012/13 target complete

Site Restoration

Site Restoration

The objective of this theme is to restore our designated sites and release them for other uses.

Our priority is to remediate hazardous materials in the legacy ponds and silos at Sellafield. We will also decommission redundant facilities at Sellafield whilst maintaining the infrastructure and capability across the site to sustain the operations of key supporting plants and services. Across the rest of the estate we will place Magnox reactors into care and maintenance, deliver Dounreay site to an Interim State and maintain Harwell and Winfrith in a safe and secure state.

Across Research Site Restoration Ltd

Target Status Commentary

Development of programme optimisation including accelerated scenarios/options

On target

2012/13 target complete

 

Bradwell

Target Status Commentary

Continued pilecap de-plant

On target

2012/13 target complete

Ponds centre bay drained and stabilised

On target

2012/13 target complete

Dessicant retrieval complete

On target

2012/13 target complete

Chapelcross

Target Status Commentary

Completion of bulk asbestos removal from heat exchangers and turbine hall

On target

2012/13 target complete

Continued hazard reduction activities towards interim Care and Maintenance

 

On target

Appropriate activities are being discharged

Dounreay

Target Status Commentary

Ongoing destruction of alkali metal on sodium wetted components from reactor decommissioning

On target

2012/13 target complete

Continue removal of spent fuel cans stored in the PFR buffer store

On target

2012/13 target complete

Dungeness A

Target Status Commentary

 Continued hazard reduction activities towards interim Care and Maintenance

On target

Appropriate activities are being discharged

Harwell

Target Status Commentary

Care and Maintenance of redundant reactors and other facilities

On target

2012/13 target complete

Decommissioning of Liquid Effluent Treatment Plant (LETP)

Behind target

Target for 2012/13 missed

Hinkley Point A

Target Status Commentary

Complete bulk asbestos removal

On target

2012/13 target complete

Hunterston A

Target Status Commentary

Pond dewatering and drainage ongoing

On target

2012/13 target complete

LLWR

Target Status Commentary

Commence site preparation for phased construction of final cap

On target

12/13 Target Complete

Ongoing implementation of the Environmental Safety Case

On target

12/13 Target Complete

Ongoing decommissioning of PCM facilities

Behind target

Milestones have been completed but late to schedule due to a change to the delivery strategy during the year

NDA

Target Status Commentary

Prioritisation of funding for high risk and hazard legacy wastes

On target

2012/13 target complete

Programme optimisation including accelerated scenarios / options

On target

2012/13 target complete

Oldbury

Target Status Commentary

Preparations for decommissioning hazard reduction

On target

2012/13 target complete

Sellafield

Target Status Commentary

First Generation Magnox Storage Pond - Commence retrieval of fuel from pond floor

On target

2012/13 target complete

Pile Fuel Cladding Silo Programme - Complete construction of the superstructure to house the equipment needed to retrieve waste from the silo

On target

2012/13 target complete

Pile Fuel Cladding Silo Programme - Complete Retrievals Access Penetration detailed design

On target

2012/13 target complete

Pile Fuel Storage Pond - Continue removal of sludge from the pond

On target

2012/13 target complete

Pile Fuel Storage Pond - Continue removal of contaminated metal for treatment and storage

On target

2012/13 target complete

Pile Fuel Storage Pond - Continue the transfer of metal from the pond for storage

On target

2012/13 target complete

Pile Fuel Storage Pond - Commence the transfer of oxide fuel from the pond for storage

On target

2012/13 target complete

Magnox Swarf Storage Silo - Complete ‘project concept’ design review for Silos Direct Encapsulation Plant

On target

2012/13 target complete

Magnox Swarf Storage Silo - Complete the Silo Emptying Plant assembly

On target

2012/13 target complete

Capenhurst - Progress site integration into URENCO

On target

2012/13 target complete

Capenhurst - Continue to process uranic residues

On target

2012/13 target complete

First Generation Magnox Storage Pond - Complete construction of Sludge Packaging Plant 1 buffer storage facility

Behind target

Target for 2012/13 has not been met

Magnox Swarf Storage Silo - Complete seismic improvements on second extension

Behind target

Target for 2012/13 has not been met

Decommissioning - Progress removal of filter gallery from Windscale Chimney Pile 1

Behind target

Target for 2012/13 has not been met

Decommissioning - Continue to retrieve and treat, for long-term storage, legacy flocculent from the flocculent storage tanks

Behind target

Target for 2012/13 has not been met

Sizewell A

Target Status Commentary

Maintain facilities in a safe state

On target

Appropriate activities are being discharged

Springfields

Target Status Commentary

 Continue the Post Operational Clean Out (POCO) and decommissioning of redundant areas

On target

2012/13 target complete

Trawsfynydd

Target Status Commentary

Continue safe-store asset care activities to support Care and Maintenance entry

On target

2012/13 target complete

Complete the strengthening of the capping roof

On target

2012/13 target complete

Complete North Lane Pond scabbling

Behind target

Final pass suspended due to optioneering to establish best practical end state.

Completion of North FED civil enabling works

Behind target

Ventilation issues and unexpected contamination screed layer.  Completion expected mid May 2013.

Winfrith

Target Status Commentary

Prepare Winfrith for Interim State in a safe and secure manner and review opportunities for optimisation

On target

2012/13 target complete

Spent Fuels

Spent Fuels

The objective of this theme is to ensure safe, secure and cost-effective lifecycle management of spent fuels.

We will manage all spent Magnox fuel to a safe and secure state and place all exotic fuels into a final disposition form. We will continue to use up the existing fuel load at Oldbury and Wylfa. On oxide fuels, we will continue to receive and manage fuel from EDF Energy* and seek to maximise value from our spent fuel management contracts.

Across Magnox Ltd

Target Status Commentary

Management of the Magnox Operating Programme (MOP) and co-ordination of Magnox fuel management activities with Sellafield and Dounreay

Behind target

Spent Fuel deliveries 359 teU.  Overall stocks of wetted Magnox fuel managed for Sellafield shutdowns in 2013/14.  Overall spent fuel delivery capability for 2012/13 was 890 teU

Chapelcross

Target Status Commentary

Completion of reactor defuelling requirements in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Dounreay

Target Status Commentary

Complete preparations and commence 'Out of Reactor' breeder fuel shipments to Sellafield

On target

2012/13 target complete

Complete the removal of fuel from PFR Reprocessing Plant

On target

2012/13 target complete

 

Dungeness A

Target Status Commentary

Completion of reactor defuelling requirements in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Oldbury

Target Status Commentary

Commencement of reactor defuelling in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Sellafield

Target Status Commentary

AGR Programme – ongoing removal of Multi-Element Bottles (MEBs) from THORP

On target

2012/13 target complete

Receive the first batch of Dounreay Fast Reactor (DFR) Breeder fuel at Sellafield

On target

2012/13 target complete

 

 Continue to receive Advanced Gas Reactor (AGR) fuel from EDF

On target

2012/13 target complete

 

Continue to reprocess Magnox Fuel in line with the Magnox Operating Programme

Behind target

Target for 2012/13 has not been met

 

Continue to reprocess oxide fuel through Thermal Oxide Reprocessing Plant (THORP) from EDF and overseas customers

Behind target
Target for 2012/13 has not been met

Sizewell A

Target Status Commentary

Continue defuelling in line with Magnox Operating Programme (MOP)

On target

2012/13 target complete

Nuclear Materials

Nuclear Materials

The objective of this theme is to ensure safe, secure and costeffective lifecycle management of our nuclear materials.

Harwell

Target Status Commentary

Progress the capability to transfer materials off site

On target

2012/13 target complete

NDA

Target Status Commentary

Progress the capability to transfer materials between sites

On target

2012/13 target complete

Work with Government on implementing any new policy regarding nuclear material

On target

2012/13 target complete

 

Sellafield

Target Status Commentary

Sellafield is the custodian of the majority of the UK's stock of plutonium and its safe secure storage is of the utmost priority. Consolidation of materials is an ongoing activity and will continue to be part of the sites mission.

On target

2012/13 target complete

Continue the safe and secure storage of plutonium in line with UK policy

On target

2012/13 target complete

Explore the consolidation of materials across the NDA estate

On target

2012/13 target complete

Springfields

Target Status Commentary

Processing historic residues to recover uranium to return to the nuclear fuel cycle.

 

On target

2012/13 target complete

Integrated Waste Management

Integrated Waste Management

The objective of this theme is to ensure that wastes are managed in a manner that protects people and the environment, now and in the future, in ways that comply with UK Government and Scottish Government policies and provide value for money. The NDA has been given responsibility for planning and implementing geological disposal in accordance with UK Government policy. This is delivered through RWMD.

Across Magnox Ltd

Target Status Commentary

Delivery of the Magnox and LLWR joint waste management plan for LLW

Behind target

All targets met or exceeded (4/5) with the exception of the VLLW component

Berkeley

Target Status Commentary

Continue active waste vaults retrieval

On target

2012/13 target complete

Continue retrieval and packaging of other ILW wastes

On target

2012/13 target complete

Bradwell

Target Status Commentary

Complete active commissioning of aqueous discharge abatement plant

Behind target

The revised schedule indicates plant will not be complete to meet this target due to design and manufacturing delays. This will not stop the site entering Care & Maintenance as planned.

Commence FED retrieval and dissolution

Behind target

The target dates  for both FED targets were very challenging and have been missed.  Progress on construction progressing to a July 2013 completion.

 

Dounreay

Target Status Commentary

Continue with the construction of the new LLW Facility

On target

2012/13 target complete

Dungeness A

Target Status Commentary

Complete retrieval and processing of Low Level Waste (LLW) sludge

On target

2012/13 target complete

Harwell

Target Status Commentary

Recovery, processing and packaging of solid ILW

On target

2012/13 target complete

 

Hunterston A

Target Status Commentary

Continued development and optimisation of solid ILW Management programme

On target

2012/13 target complete

NDA

Target Status Commentary

Focus on the Higher Activity Waste (HAW) programme

On target

2012/13 target complete

Establish with the SLCs the ILW programme including co-location potential

On target

2012/13 target complete

 

RWMD

Target Status Commentary

Utilising the improved Letters of Compliance (LoC) process (agreed in March 2012) work pro-actively with waste producers in developing disposability assessments for their range of wastes

On target

2012/13 target complete

Working with stakeholders, finalise potential candidate site identification and assessment methodologies

On target

2012/13 target complete

Deliver a robust technical programme to address uncertainties in the generic Disposal System Safety Case (DSSC) including issues associated with the new build wastes and engineering design of a Geological Disposal Facility (GDF)

On target

2012/13 target complete

Establish a Geological Disposal Facility users' group to ensure non NDA disposal requirements are fully understood

On target

2012/13 target complete

Continue work on Geological Disposal Facility programme acceleration and prepare a revised baseline programme

On target

2012/13 target complete

Progress the ability to become a wholly owned subsidiary of the NDA when appropriate

Behind target

2012/13 target complete

Support community activities to identify potential candidate sites

Behind target

RWMD provided all the technical support possible to enable this. However the decision by Cumbria County Council to withdraw from the MRWS process made the target unachievable.

 

Sellafield

Target Status Commentary

Continue to repatriate overseas owned vitrified HAL to country of origin

On target

2012/13 target complete

Continue to transfer legacy Plutonium Contaminated Material (PCM) to modern engineered stores

On target

2012/13 target complete

 Diversion of materials from LLWR in line with the LLW Strategy implementation and optimisation

On target

2012/13 target complete

Continue to receive further module deliveries for the construction of Evaporator D

On target

2012/13 target complete

Continue to process HAL through the Waste Vitrification Plant

Behind target

Target for 2012/13 has not been met

Trawsfynydd

Target Status Commentary

Complete transfer of legacy waste to the Intermediate Level Waste (ILW) store

On target

2012/13 target complete

Business Optimisation

Business Optimisation

The objective of this theme is to create an environment where existing revenue can be secured, and opportunities can be developed against criteria agreed with UK Government and the Scottish Government.

Across Magnox Ltd

Target Status Commentary

Seek to optimise electricity generation at Wylfa

On target

2012/13 target complete

Explore synergies of new build activities adjacent to NDA sites through utilisation of existing assets where appropriate to reduce impact and costs

On target

2012/13 target complete

NDA

Target Status Commentary

Evaluation of potential LLWR contract extension

On target

2012/13 target complete

Capenhurst – Transition of the Capenhurst site and operations to URENCO

On target

2012/13 target complete

 

Securing best value from NDA land

On target

2012/13 target complete

 

Wylfa

Target Status Commentary

Explore the opportunity for continued electricity generation beyond December 2012

On target

2012/13 target complete

Critical Enablers

Critical Enablers

The objective of this theme is to provide the stable and effective implementation framework that enables the delivery of our mission.

The NDA has a responsibility to deliver skills, R&D and supply chain development, to consider the socio-economic aspects of its programme and maintain effective stakeholder engagement.

Across Magnox Ltd

Target Status Commentary

Provide support to the NDA in competition for the PBO

On target

2012/13 target complete

Execute and continuously improve delivery of the Magnox Optimised Decommissioning Programme (MODP)

On target

2012/13 target complete

Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up

On target

2012/13 target complete

Establish the 'lead and learn' principle and focus on building a delivery organisation.

On target

2012/13 target complete

 

Embed a Programme Delivery Organisation across the Magnox estate and drive value through implementation of best practice

On target

2012/13 target complete

 

Across Research Site Restoration Ltd

Target Status Commentary

Provide support to the NDA in the competition for a new Parent Body Organisation (PBO)

On target

2012/13 target complete

Development of optimised decommissioning plan options

On target

2012/13 target complete

 

Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up

On target

2012/13 target complete

 

Bradwell

Target Status Commentary

Capture lessons learned for application to other Magnox sites (lead and learn)

On target

2012/13 target complete

 

Dounreay

Target Status Commentary

Complete inactive commissioning of equipment to remove breeder fuel from the DFR

On target

2012/13 target complete

Complete the new PBO baseline update to reflect the winning decommissioning strategy

On target

2012/13 target complete

Complete the design for an Un-irradiated Fuels Characterisation Facility to assay and package un-irradiated fuels for final disposition

On target

2012/13 target complete

Implementation of the socio-economic and stakeholder engagement plans

On target

2012/13 target complete

 

NDA

Target Status Commentary

Initiate the Records Management project to ensure NDA are compliant in storing and restoring documents

On target

2012/13 target complete

Re-certification of ISO9001/14001

 

On target

2012/13 target complete

Preparations for the Magnox and RSRL competitions

On target

2012/13 target complete

Embed new programme and project reporting

On target

2012/13 target complete

Improving Risk Management throughout the estate

On target

2012/13 target complete

 Embed the new Dounreay Programme into NDA plans following competition

On target

2012/13 target complete

Implementation of the Direct Research Portfolio Framework Contracts to support the development of strategy and estate wide needs and opportunities

On target

2012/13 target complete

Deliver savings from collaborative procurement across the estate

On target

2012/13 target complete

 

Oversee the delivery of the Skills and People Strategy including the Transition Framework

On target

2012/13 target complete

 

Information Governance Strategy to be approved and published which will include details on Knowledge Management and the long-term Records Management Solution

On target

2012/13 target complete

 

Oldbury

Target Status Commentary

Commencement of the organisational change programme for decommissioning

On target

Appropriate activities are being discharged

Sellafield

Target Status Commentary

Complete handover of refurbished Grid Transfers

On target

2012/13 target complete

Achieve a 20% reduction in support and overhead costs releasing revenues for decommissioning and clean-up

On target

2012/13 target complete

 Complete handover of the boiler park from Sellafield to Fellside

Behind target

Target for 2012/13 has not been met

Continue the Sellafield infrastructure enhancement programme

Behind target

Target for 2012/13 has not been met

Implementation of the focus areas of the Integrated Change Programme (ICP) across all operating units

Behind target

Target for 2012/13 has not been met

Trawsfynydd

Target Status Commentary

Capture lessons learned for application to other Magnox sites (lead and learn)

On target

2012/13 target complete

Review the opportunity for personnel and skills transfer between Trawsfynydd, Wylfa and potential new build on Anglesey

On target

Appropriate activities are being discharged

NDA

Site Restoration

Target Status Commentary

Prioritisation of funding for high risk and hazard legacy wastes

On target

2012/13 target complete

Programme optimisation including accelerated scenarios / options

On target

2012/13 target complete

Nuclear Materials

Target Status Commentary

Progress the capability to transfer materials between sites

On target

2012/13 target complete

Work with Government on implementing any new policy regarding nuclear material

On target

2012/13 target complete

 

Integrated Waste Management

Target Status Commentary

Focus on the Higher Activity Waste (HAW) programme

On target

2012/13 target complete

Establish with the SLCs the ILW programme including co-location potential

On target

2012/13 target complete

 

Business Optimisation

Target Status Commentary

Evaluation of potential LLWR contract extension

On target

2012/13 target complete

Capenhurst – Transition of the Capenhurst site and operations to URENCO

On target

2012/13 target complete

 

Securing best value from NDA land

On target

2012/13 target complete

 

Critical Enablers

Target Status Commentary

Initiate the Records Management project to ensure NDA are compliant in storing and restoring documents

On target

2012/13 target complete

Re-certification of ISO9001/14001

 

On target

2012/13 target complete

Preparations for the Magnox and RSRL competitions

On target

2012/13 target complete

Embed new programme and project reporting

On target

2012/13 target complete

Improving Risk Management throughout the estate

On target

2012/13 target complete

 Embed the new Dounreay Programme into NDA plans following competition

On target

2012/13 target complete

Implementation of the Direct Research Portfolio Framework Contracts to support the development of strategy and estate wide needs and opportunities

On target

2012/13 target complete

Deliver savings from collaborative procurement across the estate

On target

2012/13 target complete

 

Oversee the delivery of the Skills and People Strategy including the Transition Framework

On target

2012/13 target complete

 

Information Governance Strategy to be approved and published which will include details on Knowledge Management and the long-term Records Management Solution

On target

2012/13 target complete

 

RWMD

Integrated Waste Management

Target Status Commentary

Utilising the improved Letters of Compliance (LoC) process (agreed in March 2012) work pro-actively with waste producers in developing disposability assessments for their range of wastes

On target

2012/13 target complete

Working with stakeholders, finalise potential candidate site identification and assessment methodologies

On target

2012/13 target complete

Deliver a robust technical programme to address uncertainties in the generic Disposal System Safety Case (DSSC) including issues associated with the new build wastes and engineering design of a Geological Disposal Facility (GDF)

On target

2012/13 target complete

Establish a Geological Disposal Facility users' group to ensure non NDA disposal requirements are fully understood

On target

2012/13 target complete

Continue work on Geological Disposal Facility programme acceleration and prepare a revised baseline programme

On target

2012/13 target complete

Progress the ability to become a wholly owned subsidiary of the NDA when appropriate

Behind target

2012/13 target complete

Support community activities to identify potential candidate sites

Behind target

RWMD provided all the technical support possible to enable this. However the decision by Cumbria County Council to withdraw from the MRWS process made the target unachievable.